Case Study   

 

Kashagan Oil Field (Kazakhstan)

Project Theme

Construction of 270 MW Combined Cycle Power Station & Utilities Area.

Project description

Execution of all civil works, steel structure, mechanical, electrical erection, piping, instrumentation, painting and insulation works of 280 MW natural gas fired combined cycle power plant composed of gas turbines and steam turbines for the power supply for Trench 1 and 2 of Kashagan Petroleum Area.

Scope

Supply of Pipes, Valves, Fire Fighting Systems, Insulation material, Structural Steel and HVAC Systems. Installation of Insulation, HVAC and Structural Steel, Painting and Fire proofing works.